Phase 5: Preproduction

Turning a prototype that works into a design that can be made repeatedly, at the target cost, and pass its tests.

On this page
  1. What the phase involves
  2. Why the unit cost finally becomes real
  3. What comes out
  4. Typical cost and duration
  5. What to ask a firm or manufacturer about this phase

Preproduction is the phase between a working prototype and a factory. The question it answers is can this be made repeatedly, at the target cost, and pass its tests? Making one of something and making ten thousand are different engineering problems, and this phase is where the second one gets solved.

Firms that specialize in early-phase work often hand off here to a contract manufacturer or a production-focused firm. That is normal. The handoff goes better when the prototype phase ended with complete files and a clear requirements document.

Rough guess Assumed Known Possible cost 1ProjectInitiation 2Feasibility 3Proof ofConcept 4Prototype 5Preproduction 6Production
Where this phase sits. The highlighted marker is this phase. Everything to its left has been answered; everything to its right is still a range.

What the phase involves

Design for manufacturing (DFM). Every part is revisited with the production process in mind. A housing that was machined for the prototype gets redesigned for injection molding: wall thickness made uniform, draft angles added so the part releases from the mold, undercuts removed, features combined. A bracket that was laser-cut and bent by hand gets redesigned for a progressive die. Parts are combined or eliminated. Fasteners are standardized. The goal is a design that a factory can make quickly, consistently, and at the target cost.

Design for assembly (DFA). The order and method of putting the product together is designed, not left to chance. Fewer parts, fewer orientations, fewer tools, fewer chances to get it wrong.

Supplier selection. Quotes from manufacturers for each part and for assembly. Quotes at this stage are the first real production cost numbers in the whole project. Lead times, minimum order quantities, and payment terms come with them.

Tooling. Molds, dies, jigs and fixtures are designed and made. Tooling is a large one-time cost and a long lead time. It is also the point of no return for a design: a change after the mold is cut means a new mold or an expensive modification.

Pilot run. A small batch, often tens to a few hundred units, made with the production tooling and process. The pilot run finds the problems that only appear when real parts from real suppliers meet each other on a real assembly line.

Verification and certification testing. The product is tested against every requirement, formally, with records. Regulatory testing happens here: electrical safety, electromagnetic compatibility, radio, ingress protection, drop, and whatever else the market requires. Failing a certification test and revising the design is common and should be budgeted for.

Documentation. Assembly instructions, test procedures, quality standards, packaging specifications, a controlled bill of materials. A factory builds from documents, not from a conversation.

Key takeaway A prototype is designed to work. A production design is designed to be made. The two can look identical from the outside and share almost no part files.

Why the unit cost finally becomes real

Every phase before this one estimated the production cost. Preproduction measures it. Supplier quotes replace guesses, the pilot run reveals the actual yield and assembly time, and the tooling cost is a number on an invoice. The uncertainty band around the unit cost, which was very wide in Feasibility, is now narrow enough to set a retail price with confidence.

If the number is too high, this is the phase for cost reduction: alternative materials, simpler parts, different suppliers, or a requirement reconsidered. Each of these is far cheaper here than after the production order is placed.

What comes out

  • A production-ready design package: CAD, drawings, electrical files, firmware, bill of materials, assembly and test documentation.
  • Tooling, owned by whoever paid for it (check the contract; it is not always the owner).
  • Pilot-run units and the test records from them.
  • Certification reports, or a clear list of what remains.
  • A measured unit cost at the planned volume.
  • A gate decision: release to Production, revise, or pause.

Typical cost and duration

This phase has two very different kinds of cost. Labor, as in every phase: manufacturing engineers, quality engineers, project management. And tooling and pilot materials, which are hard costs paid to suppliers and often the largest single line in the whole development budget. Timelines are driven by tooling lead times and certification lab schedules, both of which are outside anyone's direct control.

Common mistake Cutting tooling from prototype files to save time. The prototype was designed to be made one at a time by a different process. The mold produces parts that do not fit, do not release, or warp, and the fix is a second mold.

What to ask a firm or manufacturer about this phase

  • "Who owns the tooling, and can it be moved to another factory?"
  • "Which certifications does this product need in each market, and who manages the testing?"
  • "What is the minimum order quantity, and what is the unit cost at that quantity versus the target volume?"
  • "What happens if the pilot run fails a test?"

Try this (15 minutes) List every custom part in the product. Next to each, write the process that would make it in production (molded, stamped, machined, cast, printed circuit board, and so on). Any part where the process is unknown is a question for this phase.